Preparations for the first concrete pouring are underway - Paks 2 EN
Preparations for the first concrete pouring are underway
The concrete batching facility at the site of the Paks II. project is already in operation and preparations are underway in the excavation pit of Unit 5 in order to start the construction of the foundation slab of the first technological building, i.e. the first concrete pouring in February 2026. According to the terminology of the International Atomic Energy Agency the new Paks nuclear power plant will be considered under construction from this milestone.
After the reinforcement is completed, the fittings to be installed are placed according to the plans, they are formed around them and finally under continuous quality control, special concrete of a quality confirmed by laboratory tests is poured. Since this activity cannot be interrupted, several concrete pumps work in parallel in order to ensure continuous work. The scale is clearly illustrated by the fact that 329 cubic meters of concrete were used to construct the first foundation slab bay. At the end of the process, the hardening and temperature of the concrete are monitored using instruments.
In the excavation pit the different work phases are therefore carried out in parallel in each bay. The levelling concrete of the different areas, the insulation of the levelling concrete, the grounding mesh works, the reinforcement and the concreting of the foundation slabs bay proceed side by side according to the so-called construction organization plan.
The levelling concrete is served by a concrete batching facility that has already been put into operation at the Paks II. site. In order to ensure the continuity of the concreting, this facility, in fact, consists of two concrete mixing units, each with three 500-ton cement silos, aggregate storage silos, loading ramps with a load capacity of 30 tons/vehicle and other equipment necessary for the concrete production technology.
As it is known, on 4 November 2025 the Hungarian Atomic Energy Authority issued the amended construction licenses for the construction of the Unit 5 control building, auxiliary building and steam cell, as well as the partial occupancy licence for the soil improvement of the Unit 5 nuclear island. Obtaining the licenses was a key step in starting the concreting works, including the construction work of the foundation slab of the Unit 5 nuclear island.